qualification

qualified personnel

Material

Pos.DesignationArticleNumber
01GIF-61 unit boardT284991

Required material

  • Torx screwdriver size 20

procedure

ATTENTION!

Working with the unit requires knowledge of the safety instructions and quick guide. That's why:

Read the safety instructions and quick guide carefully before starting any work. The basic requirement for safe work is compliance with all safety instructions and careful action by qualified qualified personnel to prevent accidents involving personal injury and property damage.

NOTE!

The configuration and calibration data are stored on the GIF-61 (A 4) unit board and are therefore lost when replaced.

Cool down and turn off the unit

  • On the basic screen, tap the function button ().
    → The unit cools down until the temperature is lower than the cooling temperature. The unit then switches off.

  • Switch off the main switch (QS 1), pull out the mains-connector.

Open front

  • Open the front door and fold the front completely down by loosening the two Torx screws.

Replace unit board

  • Remove all connectors on the GIF-61 (A 4) unit board.
  • Push the mounting straps (2) of the GIF-61 (A 4) unit board outwards.
    → The circuit board can now be lifted out.
  • Insert the new GIF-61 (A 4) unit board into the appropriate recesses.
    → Check whether the mounting straps (2) are locked in place.
  • Reconnect all plug connections to the GIF-61 (A 4) unit board.
    → Check whether all connectors are correctly attached.

Close front

  • Fold up the front and secure 2x Torx screws.

Switch on the unit

  • Connect the mains-connector and switch on the main switch (QS 1).
    → If necessary, The unit automatically software-update.

NOTE!

If the configuration is incomplete, the corresponding error message appears on the screen. The error message can be ignored because a reset complete is then carried out.

Reset data

  • Tap the profile button () on the basic screen.
  • Select [User Profile].
  • Set the parameter to “Maintenance.”
  • Select [Service] > [Configuration] > [Reset Complete].
    → Access is via the code "1.2.
  • Tap the reset symbol () to reset all data.

Configuring a unit

  • Select [Service] > [Configuration].
    → Access is via the code "1.2.
  • Reconfigure the unit. When configuration, follow the information on the unit's nameplate. The following parameter settings are required:
    • unit number
    • year of manufacture
    • Temperature
    • hydraulic system
    • unit housing size
    • Heating type
    • pump type
    • Cooling type
    • Mains voltage (U N)

calibrating the unit

ATTENTION!

danger
incorrect calibrating Incorrect
calibrations can lead to device malfunctions. That's why:

  • Verify calibrating

Calibrate pressure measurement

  • Make sure the unit is depressurised.
    → The unit's pressure gauge must read 0.0 (±0.3) bar.
  • Remove the hydraulic connections on the Main line and Return line lines.
    → The unit's pressure gauge must read 0.0 (±0.3) bar.
  • Select [Display] > [Actual Values] > [System Pressure] or [main Line Pressure].
    → The system pressure must display 0.0 (±0.1) bar.
    If there is a deviation of >0.1 bar, the unit's pressure sensors must be checked. In the case of larger linear errors, a general deviation (offset) from the pressure sensor must be corrected.
    → [Service] > [Calibrating] > [Pressure] > [Pressure sensor 1 Offset] (System Pressure) or [Pressure sensor 2 Offset] (main line pressure).

Control:

  • Select [Display] > [Actual Values] > [System Pressure] or [main Line Pressure]
    → The system Pressure
    must display 0.0 (±0.1) bar. If this act not the case, Repeat The Calibrating Of The Pressure Sensor.

Calibrate Flow rate measurement

  • Install the hydraulic line with shut-off valve (e.g. HB-TP180 checking facility) between the Main line and Return line connection.
  • In normal operation, operate the unit at 40°C for at least 10 minutes.
  • Select [Service] > [Calibrating] > [Flow Rate] > [Flow rate offset (internal)].
    → Set the parameter to 5 l/min.
  • Close the shut-off valve between Main line and Return line and wait for 1 minute.
  • Read the current flow rate.
  • Set the parameter [Flow rate offset (internal)] using the following calculation:
    → New offset = 5 L/min — 'current flow' [flow Rate].
  • Open the shut-off valve.

Control:

  • In normal operation, operate the unit at 40°C for at least 10 minutes.
  • Close the shut-off valve between Main line and the Return line.
    → The flow rate drops to 0 l/min and the “Flow rate zero” alarm message is delayed.
  • Acknowledge acknowledge alarm and open the shut-off valve.

Check function

  • Switch on the unit using the I/O button (), check the tightness and function of the unit.
  • Check the device functions (regulate for the desired set value).
  • Switch off the unit using the I/O button ().
    → The unit switches off and, if necessary, is cooled and depressurised.
  • Switch off the main switch (QS 1).